By Nicolas Delgado | Volunteer
Dear donors,
It is with immense pleasure that we share with you the great progress of this work!
In just 3 months we have an enclosed space that little by little (or rather by leaps and bounds) is taking shape as a multipurpose room.
The photos speak for themselves. But it is worth repeating that we have finished the foundation platea and we have already built the exterior walls and the roof. With this, the space that is to be a multi-purpose hall now has its definitive shape and size.
We are working on the electrical installation inside the hall. In a short time we will begin to make the subfloor and the floor folder.
As for the exterior, we are finishing covering the roof with metal sheets, as well as advancing in the construction of the access ramp to the hall and finishing the flower beds that will be located in the front of the building.
We hope to be able to move forward with the construction of the gallery and roofed space that will join the old building with the new one.
The progress of this work depends today more than ever on the contribution of donations like yours. Please continue to support us!
Until the next report! Cheers!
Engineering Without Borders Argentina
Project reports on GlobalGiving are posted directly to globalgiving.org by Project Leaders as they are completed, generally every 3-4 months. To protect the integrity of these documents, GlobalGiving does not alter them; therefore you may find some language or formatting issues.
If you donate to this project or have donated to this project, you can receive an email when this project posts a report. You can also subscribe for reports without donating.
Support this important cause by creating a personalized fundraising page.
Start a Fundraiser