By Lameck Mbiriyaza Chirwa | Project Leader
Dear donor (Mulibwanji)
I write to you to give an update about the progress of the library extension project. As you already know in my last report I said that the project started well and we have now managed to dig the foundation and lay out the building design.
I am glad to say that on 15 November 2021, we will start constructing the foundation of the building. We hope that when the rains starts in December the foundation will be completed so that the building cannot be damaged.
We are still receiving donations for this project as we have not yet accumulated all the funds that we planned to generate.
We wish you a blessed holiday and happy New Year.
God bless you
Links:
Project reports on GlobalGiving are posted directly to globalgiving.org by Project Leaders as they are completed, generally every 3-4 months. To protect the integrity of these documents, GlobalGiving does not alter them; therefore you may find some language or formatting issues.
If you donate to this project or have donated to this project, you can receive an email when this project posts a report. You can also subscribe for reports without donating.