By Karlheinz Neumann | Founder and Project Leader
Special note: We are expanding our portfolio in Afikpo to the health sector with clean drinking water and emergency medical aid. Although our project is not only focussing on school renovation we will keep the project name, as we do not want to lose some anonymous donors which cannot be informed. Almost all activities are offered in the same town and children from school will mainly benefit.
For today we will give you an update on our successful school renovation projects.
The Canteen
In January 2023, the newly built school canteen was handed over to the school management of the Amuro/Mgbom school with a little celebration.
For a number of children who also have lessons in the afternoon, a small meal is prepared privately by some families at lunchtime and sold at school. Children who can afford it pay 250 naira, about 1/2 USD, for a simple meal without meat. So far, food has always been eaten outdoors. With the construction of the school canteen, the students now have the opportunity to eat while sitting. On average, 200-250 school children use this opportunity every day.
The school management and the teachers are very happy about the next step into a bright future for the school.
Total costs: 15,000 USD.Two toilet facilities
Also in January, the day finally came to ceremoniously hand over the two long-awaited toilet blocks to the “Primary and Secondary School” in Amuro/Mgbom. For teachers and students, this is an improvement that is hard to describe. After more than 20 years, there are sanitary facilities on the school premises again.
Ten toilets with washing facilities are available for both the primary and the secondary school. That may still not be enough for 1,700 students and 80 teachers, but it is a big step forward. The faeces and waste water are drained through pipes into appropriate pits.
After the renovation of the U-Block, the provision of drinking water on the school premises, the construction of the school canteen and the sanitary facilities, a first major milestone has been reached. However, there are still nine other buildings to be renovated. When and how we will proceed with the renovation will be clarified by the end of the year. The big water project is still pending, as well as the daily care of needy families and emergency medical aid.
Total costs for the construction of the sanitary facilities: 35,000 USD.We hope all of you as our great supporters in Nigeria will continue giving a helping hand for the poors in Ebony State region. Thank you so much.
By Karlheinz Neumann | Founder and Project Leader
By Karlheinz Neumann | Project Leader and Founder
Project reports on GlobalGiving are posted directly to globalgiving.org by Project Leaders as they are completed, generally every 3-4 months. To protect the integrity of these documents, GlobalGiving does not alter them; therefore you may find some language or formatting issues.
If you donate to this project or have donated to this project, you can receive an email when this project posts a report. You can also subscribe for reports without donating.
Support this important cause by creating a personalized fundraising page.
Start a Fundraiser