By Nicolas Delgado | Volunteer
Dear donors,
We are very pleased to share with you all the progress of this project since our last report.
We are going through the last stages of this project. The last 3 remaining roofs are being completed and are expected to be finished during the month of July. As for the cisterns, 3 are under construction and the construction of the last 3 remaining cisterns will start next month. With them, the activities of this project will be concluded.
The completion of the project was previously planned, but due to weather-related situations and the community's own activities, the closing date has been postponed. In our next report we hope to be able to share that the tasks have been completed in their entirety.
It is important to note that during the month of June workshops were held with the community on the pumps used in the cisterns and how to extract water from them.
Thank you very much and we hope you will continue to support this project.
Cheers!
Engineering Without Borders