By Nicolas Delgado | Volunteer
Dear donnors,
We are more than happy to share with you all a new update about this beautiful project!
During January and February, the progress of the work was delayed, due to the large number of rainy days and the fact that this is a period when many people move to work at other sites.
This was expected, but in any case, the project is at an advanced stage. Only 3 cistern tanks remain to be completed out of 33 planned. And progress has been made on the construction of the roofs, which are almost complete.
As next steps, we will soon begin to pipe conections between the existing roofs and the tanks, which was delayed due to the reasons explained above.
The project is expected to be finished by the end of April! So we will be happy to share progress in our next (and perhaps last) report, showing you some (or all) the systems completed already.
Please keep on supporting this great project, now that we are so close to complete it!
Cheers!
Engineering Without Borders Argentina