By Carlos Torrado | Project Leader
At the moment, the final stage of repairs for this project is on standby awaiting for clearance from FEMA and COR3 reviews.
We are hoping to have the approval from FEMA within the next 90 days.
Roof sealing and paint work has been completed as well as installation of alarm system. What remains is the hangar for official vehicles and that part of the project is what is PENDING approval from FEMA.
We are very grateful for donations to this project. Please be assured that as soon as construction of Hangar begins we will notify all donors. Also, in mid November we received a visit form two members of Global Giving's staff who conducted a site inspection of the project and they confirmed that all repairs of this project had been completed except for the hangar which again, is pending FEMA approval.
Project reports on GlobalGiving are posted directly to globalgiving.org by Project Leaders as they are completed, generally every 3-4 months. To protect the integrity of these documents, GlobalGiving does not alter them; therefore you may find some language or formatting issues.
If you donate to this project or have donated to this project, you can receive an email when this project posts a report. You can also subscribe for reports without donating.