We are glad to announce that owe have completed 100 sessions with neighbors and volunteers working 8-hours days to complete this project! Please check the pictures to see how this amazing project keeps progressing.
The roof of the building is completed and all the masonry and concrete components of the project are finished. We also started doing the landscaping of the project. More than 300 sq mts of a recreational garden specially designed for small childrens.
Below you'll find some highlights of the upcoming tasks.
Please keep on supporting this project!
Engineering Without Boarders Argentina.
Tasks completed:
Concrete roof slab specially designed for the rainwater harvest system
General electrical assembly.
Finished all concrete foundations and slabs.
General landscape leveling and soil adequation.
Tasks under way:
Floor finishes for outdoor corridors and classrooms.
600lts Rainwater collection system.
outdoor corridors' roof structure
External and internal insulation.
Grass placement for landscape.
Construction of a vegetable plot for children.
Next tasks:
Installation of external and internal insulation of the building for a comfortable and low maintenance building.
Installation of external and internal material finishes of the building.
Installation of lights and electrical appliances.