We are very pleased to be able to inform you of the important progress of this work.
The building has been in its final shape for some time now. At this moment we are working on the interiors, and the idea is that the project will be finished in March of next year!
All the enclosures have been completed with the placement of the carpentry (windows and doors).
We are putting up the durlock for the walls and interior divisions.
We are also working on the ceiling, which is expected to be finished in two weeks.
Next steps are to start with the electrical installations and the assembly of the bathrooms.
We have reached this point (among other things) thanks to your support. Join us in this final stretch of the project so that more women can have access to decent work.
Thank you very much!!!
Engineering without Borders Argentina
Project reports on GlobalGiving are posted directly to globalgiving.org by Project Leaders as they are completed, generally every 3-4 months. To protect the integrity of these documents, GlobalGiving does not alter them; therefore you may find some language or formatting issues.
If you donate to this project or have donated to this project, you can receive an email when this project posts a report. You can also subscribe for reports without donating.