By Nicolas Delgado | volunteer
Dear Donors,
From Engineering Without Borders Argentina we would like to share with you a brief update on this project.
After several months of production and preparation, we assembled the closing plates, managing to have all the walls of the building already in December!
After this, the metal structure that supports the roof was assembled, and in the first days of the year (February 2023) all the roof sheets were placed.
With the roofed room, next steps consist of carrying out sealing, coating, flooring and opening tasks.
Please keep supporting this amazing project.
Thanks a lot!!!
Engineering Without Borders Argentina