By Nicolas Delgado | Volunteer
As we sahred with you last time, the water tanks are already finished. The last month, we started the construction of the new roofs and the adaptations and repair of the existing ones.
The activities progressed more slowly during the months of January and February due to the intense climate in the region during summer and the period of vacations. But we restarted again fully recharged during March!
At this moment, there are 9 families which have the systems almost ready: The roofs and connections are almost finished and the systems are closer to become a reality!!!
Another 8 families started working and preparing everything for the construction of the roofs. As you can see in the pictures, more structures for new roofs are already started. The goal is to have them finished by the end of April.
Than you very much to keep suporting this project. We are realy happy to share with you these incredible advances in the works!
Cheers and until next time!
Engineering without Borders Argentina
Project reports on GlobalGiving are posted directly to globalgiving.org by Project Leaders as they are completed, generally every 3-4 months. To protect the integrity of these documents, GlobalGiving does not alter them; therefore you may find some language or formatting issues.
If you donate to this project or have donated to this project, you can receive an email when this project posts a report. You can also subscribe for reports without donating.